Delhi High Court Blocks ₹213 Crore SAIL Payout Over Unstamped Arbitral Award

The Delhi High Court has refused to release ₹213.24 crore deposited by the Steel Authority of India Limited (SAIL) in enforcement proceedings arising from an arbitral award in favour of British Marine PLC. The Court held that the arbitral award could not presently be executed because the original award was unavailable before the Court and the award had not undergone the requisite stamping formalities.

The decision, delivered by Justice Vinod Kumar on October 1, 2026, highlights the importance of complying with statutory stamp-duty requirements even at the stage of enforcing an arbitral award.

Background of the Dispute

The dispute originated from a Contract of Affreightment dated December 5, 2007, between SAIL and British Marine PLC concerning the transportation of coking coal to India. The contract contained an arbitration clause providing for disputes to be resolved in India under the Arbitration and Conciliation Act, 1996.

Disputes subsequently arose between the parties concerning performance of the contract. A three-member arbitral tribunal was constituted, and after prolonged proceedings, an arbitral award was pronounced on September 13, 2018.

SAIL challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996. The challenge was dismissed on October 13, 2025. SAIL subsequently pursued an appeal under Section 37, which was also dismissed by a Division Bench of the Delhi High Court on September 17, 2026.

₹230.33 Crore Deposited During Enforcement Proceedings

During the enforcement proceedings, SAIL deposited approximately ₹230.33 crore with the Registrar General of the Delhi High Court pursuant to earlier court orders.

Out of this amount, ₹17.09 crore had already been released to British Marine against a bank guarantee.

After SAIL’s Section 34 challenge and subsequent Section 37 appeal were dismissed, British Marine sought release of the remaining ₹213.24 crore.

However, the issue of stamp duty on the arbitral award became central to the Court’s consideration.

Why Did the Delhi High Court Stop the ₹213 Crore Release?

The Court noted that the original arbitral award was not available before it. According to the proceedings, the original award was lying in a sealed cover with the Supreme Court pursuant to directions issued during earlier litigation.

The Court observed that an arbitral award is a chargeable instrument under the applicable stamp-duty provisions. However, the copy of the award could not be stamped or impounded in place of the original.

Consequently, the Court held that the unstamped award could not presently be executed and therefore the amount lying deposited with the Court could not be released to the decree-holder.

This meant that although the challenges to the award under Sections 34 and 37 had already been unsuccessful, the enforcement process could not proceed to release of the balance amount until the stamp-duty issue was properly addressed.

Court Provides a Route for Future Enforcement

Importantly, the Delhi High Court did not permanently prevent British Marine from obtaining the money.

The Court granted liberty to British Marine to:

1. Bring the original arbitral award before the High Court;

2. Complete the requisite stamp-duty formalities; and

3. File a fresh application seeking release of the amount.

Thus, the order operates as a procedural and statutory hurdle to enforcement rather than a determination that British Marine is not entitled to the awarded amount.

What Happened to the ₹17.09 Crore Bank Guarantee?

The Court separately dealt with the ₹17.09 crore bank guarantee that had been furnished by British Marine against the amount previously released.

Since that amount had already been released and SAIL’s Section 34 challenge and Section 37 appeal had been dismissed, the Court found no continuing purpose in retaining the security and directed discharge of the bank guarantee.

Therefore, the Court’s treatment of the two amounts was different:

• ₹17.09 crore: Bank guarantee discharged.

• ₹213.24 crore: Release refused for the present because of the unstamped award and absence of the original before the Court.

Significance of Stamp Duty in Arbitration Enforcement

The judgment is significant for parties involved in arbitration because it demonstrates that obtaining an arbitral award is not necessarily the final procedural step.

An award may still have to satisfy applicable statutory requirements before it can be effectively enforced. The Delhi High Court’s own website has also published a July 13, 2026 practice direction concerning payment of stamp duty on arbitral awards in execution petitions under Section 36 of the Arbitration and Conciliation Act, 1996.

This reinforces the practical importance of addressing stamp-duty compliance when an award moves from the arbitral stage to the execution stage.

Relationship Between Sections 34, 37 and Enforcement

The case also illustrates the different stages of judicial intervention in arbitration.

Section 34 – Setting Aside an Award

Section 34 provides a mechanism for challenging an arbitral award before the competent court on the statutory grounds specified in the Arbitration and Conciliation Act.

In the SAIL-British Marine dispute, SAIL’s Section 34 challenge was dismissed in October 2025.

Section 37 – Appeal

Section 37 provides for appeals in specified circumstances under the Arbitration and Conciliation Act.

SAIL’s appeal against the Section 34 decision was dismissed by the Delhi High Court’s Division Bench on September 17, 2026. The judgment records that the arbitral award dated September 13, 2018 was upheld.

Enforcement

Even after challenges to an award have been rejected, the decree-holder must satisfy the procedural requirements applicable to execution.

The present order demonstrates that the conclusion of Section 34 and Section 37 proceedings does not automatically eliminate other statutory requirements relevant to enforcement.

Key Legal Takeaways

The Delhi High Court’s order carries several practical lessons for businesses and parties involved in arbitration:

1. Stamp duty can directly affect enforcement.

An arbitral award must comply with applicable stamp-duty requirements before enforcement can proceed.

2. The original award can become crucial.

Where the original award is required for stamping or other statutory purposes, merely having a copy may not resolve the issue.

3. Arbitration litigation does not end with the award.

Parties must carefully manage the transition from arbitration to Section 34 proceedings, appeals and eventual execution.

4. Procedural compliance remains important even for substantial awards.

The fact that a very large sum is involved does not dispense with statutory requirements.

5. The order does not finally extinguish the decree-holder’s claim.

British Marine was expressly given liberty to complete the necessary formalities and approach the Court again for release of the balance.

Conclusion

The Delhi High Court’s decision in the British Marine PLC v. Steel Authority of India Limited proceedings demonstrates the importance of statutory compliance during enforcement of arbitral awards.

The Court did not reopen the merits of the arbitral dispute while deciding the October 1, 2026 application. Instead, the immediate question was whether the ₹213.24 crore deposited with the Court could be released when the original award was unavailable and the requisite stamping formalities had not been completed. The Court answered that question in the negative for the present.

For companies and commercial parties relying on arbitration, the case serves as a reminder that effective dispute resolution requires attention not only to the merits of the award but also to the statutory and procedural requirements governing its enforcement.